A builder contacted you for a project management work in order to plan a medium scale building project
Ask Expert

Be Prepared For The Toughest Questions

Practice Problems

A builder contacted you for a project management work in order to plan a medium scale building project

Task C

A builder contacted you for a project management work in order to plan a medium scale building project. He knew all the different activities of the job, their precedence and their average durations which he shared with you. They are shown on the table below.


Required:

1. Draw a network diagram and conduct the forward and backward pass.

2. State the duration of this project and the critical path.

3. Explain, without doing any calculation, what would happen to the project if the actual duration of activity A is two weeks.

Note: The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. Each activity should be described using the notation shown in class as follows:


Hint
StatisticsA medium-scale referred to a business that is often the difficult middle or small of its industry but largely gets the discounts and services afforded to small businesses and too small to have the weight and standing approved to large initiatives....

Know the process

Students succeed in their courses by connecting and communicating with
an expert until they receive help on their questions

1
img

Submit Question

Post project within your desired price and deadline.

2
img

Tutor Is Assigned

A quality expert with the ability to solve your project will be assigned.

3
img

Receive Help

Check order history for updates. An email as a notification will be sent.

img
Unable to find what you’re looking for?

Consult our trusted tutors.

Developed by Versioning Solutions.