A project network is shown below

3. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

 

Activity

Precedence Activities

Activity

Time (weeks)

 

ES

 

EF

 

LS

 

LF

 

Slack

Critical

Path?

A

--

5

 

 

 

 

 

 

B

--

4

 

 

 

 

 

 

C

--

8

 

 

 

 

 

 

D

A, B

4

 

 

 

 

 

 

E

C

12

 

 

 

 

 

 

F

C

10

 

 

 

 

 

 

G

D, E

3

 

 

 

 

 

 

H

E

2

 

 

 

 

 

 

I

E, F

5

 

 

 

 

 

 

a. Draw the project network. 

b. Complete a row for each activity under the column headings below.

c. Determine the Critical path

Hint
Accounts & FinanceA project network is a graph that depicts the activities, length, and interdependencies of tasks inside your project, according to accounts and finance....

Know the process

Students succeed in their courses by connecting and communicating with
an expert until they receive help on their questions

1
img

Submit Question

Post project within your desired price and deadline.

2
img

Tutor Is Assigned

A quality expert with the ability to solve your project will be assigned.

3
img

Receive Help

Check order history for updates. An email as a notification will be sent.

img
Unable to find what you’re looking for?

Consult our trusted tutors.

Developed by Versioning Solutions.