Question 3
Table below shows the progress of a project from the A to activity F. Assume there are other activities below activity F that are yet to be completed.
a. Calculate CV and SV for the activities of the project completed so far (A to F).
b. As a project manager you have been asked to report on the status of your project at the end of Activity F. Your stakeholders want to know, based on your EVM analysis of the table above, whether the project is likely to finish on time and within budget. Show your work and justify your answers.
c. Would your conclusions change if activities C and D were the only 2 activities on the critical path? Explain your reasoning.