Berwick Pty Ltd manufactures a product with the following standard costs:
Direct materials: 40 metres @ $2.7 per metre $108
Direct labour: 8 hours @ $18 per hour $144
Total standard prime cost per unit of output $252
The following information pertains to the month of July 2020:
Direct material purchased: 42,000 metres @ $2.76 per metre = $99,360
Direct materials used: 36,000 metres
Direct labour: 7,200 hours @ $18.30 per hour = $131,760
Actual July 2020 production was 1,000 units.
Required:
Compute the following variances for the month of July, indicating whether each variance is favourable or unfavourable:
1. Direct material price variance.
2. Direct material quantity variance.
3. Direct labour rate variance.
4. Direct labour efficiency variance.