Build well contracts Limited under took a contract for Rs. 10,00,000 on 1st April

Question 4

Build well contracts Limited under took a contract for Rs. 10,00,000 on 1st April 2019. On 31st March 2020 when the accounts were closed, the following details about the contract were gathered:


The contract contained an escalation clause which read as follows :

“In the event of increase of prices of materials and rates of wages by more than 5%, the contract price would be increased accordingly by 25% of the rise of the cost of materials and wages beyond 5% in each case”

It was found that since the date of signing the contract agreement, the prices of materials and wages increased by 25%. The value of work certified does not take into account the effect of the above clause.

Prepare the Contract Account.

Hint
Accounts & Finance The contract price is the cost for the labor and products to be gotten in the agreement. The agreement value assists with deciding if an agreement might exist. On the off chance that the agreement cost is excluded from the composed agreement, then upon suit the court might hold that an agreement didn't exist....

Know the process

Students succeed in their courses by connecting and communicating with
an expert until they receive help on their questions

1
img

Submit Question

Post project within your desired price and deadline.

2
img

Tutor Is Assigned

A quality expert with the ability to solve your project will be assigned.

3
img

Receive Help

Check order history for updates. An email as a notification will be sent.

img
Unable to find what you’re looking for?

Consult our trusted tutors.

Developed by Versioning Solutions.