1. Refer to Figures 6.6 and 6.7. Why is the earliest start time for ‘‘Review Comments & Finalize Questionnaire’’ day 33? Why is the earliest finish time day 38?
2. Refer to Figures 6.10 and 6.11. Why is the latest start time for ‘‘Mail Questionnaires & Get Responses’’ day 40? Why is the latest finish time day 105?
3. What is meant by the term slack as applied to a particular activity? What is the difference between positive slack and negative slack? How is it calculated?