Your group of two is required to explain the theory behind a Project Report
Assessment Two: Project Report
Your group of two is required to explain the theory behind a Project Report, and to develop a Project Report based on the scenario below. You must draw heavily on the theory contained in the textbook and the PMBoK. You are expected to include all the relevant sections shown in the textbook, and model your tables on the relevant textbook exhibits.
There are two parts to your project:
1. The first section will discuss the theory behind each element of the project report (2.1 – 2.12). Using appropriately cited paraphrasing, you are expected to draw on the textbook description for each section. Please note that because there is such an emphasis on the textbook, all in-text citations MUST include the page numbers.
2. The second section of the assessment is your actual project report, based on the scenario below. The project report must follow the following sections:
2.1. WBS
2.2. RACI Chart
2.3. Schedule 1 – Gantt
2.4. Schedule 2 - AoN
2.5. Resource overloads
2.6. Budget
2.7. Progress Reporting (Timelines)
2.8. Progress Reporting (EVM)
2.9. Risk Management
2.10. Change Management
2.11. Stakeholder identification & communication
2.12. Project Closure
Beachside cottage
You have inherited an old beachside cottage. You have visited the site and made an inspection. The house needs a great deal of repair work to make it liveable. You have itemised the most important things that need to be done and think it will take a team of workers about 2 weeks to complete.
You plan to use this house for vacations and as a rental property through Airbnb. In fact, some of your work colleagues have already expressed interest in renting it soon as the property is finished. You have obtained a loan from the bank of $20,000 - that believe that will give you enough money to buy the supplies and have a spending budget with help from a local contractor and two apprentices. You yourself have committed to working 80 hours over your vacation to fix up the house, but you are unskilled at carpentry. Your vacation of two weeks starts on Monday the 1st of June, and you prefer to be present when the contractor is on site. Assume you, the contractor and his apprentices1 all can work up to 8 hrs per day, 5 days per week.
You expect that within 2 years of renting the property you will have earned enough money to repay the bank loan.
Continually ask yourself the question “when this is done, what else can I start now, or which things can I do at the same time?”.
Please note while working on this project, many assumptions are made that appear unrealistic, such as for example the wages, or constraints around who can do what. The main reason behind these decision has been to create an example that is easy for you to work on, while keeping it within small boundaries.
The following List of Most Important Fixes and Project Customer Trade-Off Matrix are provided to you as background to the project; they are part of the Business Case.
List of Most Important Fixes (not necessarily in order of schedule or priority):
1 Purchase supplies
2 Hang new curtains
3 Repair wooden shutters
4 Paint shutters
5 Hang shutters
6 Repair wooden porch
7 Repair wooden floor
8 Sand floor
9 Refinish (seal) floors, including porch
10 Paint ceilings
11 Paint doors
12 Paint interior walls
13 Paint exterior walls
14 Wash exterior windows
15 Wash interior windows
Hint
Management "WBS
or work breakdown structure is a key project deliverable that organizes
the team's work into manageable sections and visually defines the scope
into manageable chunks for a project team to understand since each
level of the work breakdown structure provides further definition and
detail. PMBOK (Project Management Body of Knowledge) defines WBS as a
deliverable orie...
"WBS
or work breakdown structure is a key project deliverable that organizes
the team's work into manageable sections and visually defines the scope
into manageable chunks for a project team to understand since each
level of the work breakdown structure provides further definition and
detail. PMBOK (Project Management Body of Knowledge) defines WBS as a
deliverable oriented hierarchical decomposition of the work to be
executed by the project team.
RACI
(which is Responsible, Accountable, Consulted and Informed), the RACI
chart is a matrix of all the activities or decision making authorities
undertaken in an organisation set against all the people or roles. And,
at each intersection of activity and role it is possible to assign
somebody responsible, accountable, consulted or informed for that
activity or decision."