A defense contractor in Dallas has six jobs awaiting processing

Problem 4

A defense contractor in Dallas has six jobs awaiting processing. Processing time and due dates are given in the table. Assume that jobs arrive in the order shown.

a) Determine the schedule for the jobs by using (a) the Earliest Due Date (EDD) rule and (b) the Shortest Processing Time (SPT) rule. 

b) For both EDD & SPT, calculate the average flow time, average lateness. Which sequence company should follow as per you?


Hint
ManagementEDD is the Earliest Due Date. Also, the EDD sequencing rule is that the jobs are processed according to the due date, which is earliest due date first. It is completed before the due date under the EDD rule. Now, the average flow time is 13.98 days along with the average lateness is -1.22 days. ...

Know the process

Students succeed in their courses by connecting and communicating with
an expert until they receive help on their questions

1
img

Submit Question

Post project within your desired price and deadline.

2
img

Tutor Is Assigned

A quality expert with the ability to solve your project will be assigned.

3
img

Receive Help

Check order history for updates. An email as a notification will be sent.

img
Unable to find what you’re looking for?

Consult our trusted tutors.

Developed by Versioning Solutions.