QUESTION 3:
Note: Time units are in weeks.
(a) How many minimum resources required executing the above schedule as it is without any resource constraint?
(b) Refer to the network on previous page; construct the resource loading schedule when only 7 resources are available.
Use Minimum slack, smallest duration, lowest Id heuristic.
(Must use this given Template BELOW and it must be typed, Don’t change the font)
(c) List the order in which you scheduled the activities of the project.
(d) What is the project completion time after loading all the resource?
(e) After loading all activities, state slacks for each activity.