QUESTION 6
Consider a complex asset whose repairs are minimal. You have been tasked with finding the optimal replacement time for the asset. To this end, do the following:
a. Consider the failure times below in days. Fit a Power Law NHPP model to the data. You may use Excel or MATLAB, but you must provide plots/hand calculations/explanations of what you are doing.
b. Find the optimal replacement time if the cost of replacement is = 1,000,000 AUD and the cost of failure is 10,000 AUD.